Talking Transportation: Rail Cars a Year Late in Delivery
By Jim Cameron
Special to WestportNow
It’s the question I am asked almost every day: “When are the new rail cars coming?” The answer: “Later than we’d thought.”
Yes, the new M8 rail cars, which lawmakers authorized in 2005 and we hoped would be in service late this year, won’t be in service until late 2010--a year later than planned.![]()
The first M8 rail cars as they were prepared for their journey from Japan to Connecticut. (CLICK TO ENLARGE) Contributed photo
We on the Connecticut Rail Commuter Council (a state-appointed watchdog group) have been tracking the progress of the M8s from engineering design to focus groups on the interiors to initial “crush tests” (which they failed).
Every month we ask if there are any delays, and the Connecticut Department of Transportation (CDOT) says “no, we’re right on track.”
Initially the plan was to have a set of prototype “pilot” cars delivered by “late 2008.”
(Look it up. It’s still on the CDOT Web site.) Those cars would then undergo testing for four to six months while production continued on the “revenue” cars, which would be held out of service until the tests were complete.
That probably meant we’d be able to ride in the new M8s by April or May of 2010, about 16 or 17 months later than planned. But the time line is now slipping further.
At our September Commuter Council meeting, CDOT Commissioner Joe Marie said that the M8s manufacturer, Kawasaki, had been having problems with suppliers delivering steel later than planned. And their sub-contractors (who account for 60 percent of the cars) were also delayed.![]()
Interior of the new M8 rail cars. (CLICK TO ENLARGE) Contributed photo
Marie also said that the planned delivery schedule of 10 cars per month was extremely ambitious as railcar makers have a “deplorable record” of keeping their production promises. Marie should know, having worked for Bombardier in years past.
But wait--it gets even worse. By the time the Commuter Council met in October, this time with Metro-North President Howard Permut, the delays had been stretched. Permut said it would be months before even the test cars arrive, meaning the four to six months of testing would delay putting the cars in service until “late 2010”.
And that assumes that everything goes well and no serious problems are found during the testing.
Those tests are crucial as we’re spending $713 million on the first 300 cars. These cars should last 30 years, if they live up to their warranty. That’s why the first prototypes have to be run into the ground until something breaks.
And if some component does fail, Kawasaki will have to go back to retrofit a “fix” onto all the cars in production, both in Kobe, Japan and Lincoln, Neb.
Time line is slipping for new M8s. (CLICK TO ENLARGE) Contributed photo
Mind you, there is some good news in all of this mess. First, Kawasaki is paying millions of dollars in penalties for the delays. And second, the plans for a fare hike to pay for the new cars is also delayed.
We commuters are a patient bunch. We’ve waited a decade beyond when our old fleet should have been retired, and I guess we can wait a few more months.
But what we cannot wait for any longer is candor and honesty from CDOT, an agency whose credibility is in tatters.
The long needed New Haven Railyard facility morphed from a $300 million project in 2005 to $1.2 billion in 2008. Gov. M. Jodi Rell was incredulous and ordered a $630,000 study of the ballooning costs.
A rework of the plan brought the cost down to $850 million. But just opened bids for Phase One of the project, expected to cost $261 million, came in at $125 million.
It’s a long way from $300 million to $1.3 billion and from $261 million to $125 million. And along the way people start wondering if anyone has a clue about estimating costs. All we need are honest answers, not excuses.
Get the new M8 prototypes, start testing them and please, be honest about any further delays.
_________
(Editor’s Note: Jim Cameron has been a commuter out of Darien for 18 years. He is chairman of the Connecticut Rail Commuter Council, a member of the Coastal Corridor Transportation Investment Area, and the Darien Representative Town Meeting. The opinions expressed here are his own. You can reach him at or http://www.trainweb.org/ct. For the full collection of “Talking Transportation” columns, visit http://www.talkingtransportation.blogspot.com
Comments: Comment Policy
Jim, as predictable and appalling as this latest delay is, there may be a light at the end of the proverbial tunnel. On the same day you posted this, Warren Buffet announced purchase of the Burlington Northern railroad for $34 BILLION and described it as a “an all-out bet on the future of this country.” An impressive vote of confidence in railroads I think. Let’s hope CDOT and our state politicians get the hint.
I saw the “test” train running on Sunday morning. i was sitting at the South Compo Greens Farms light and saw them in the distance on the overpass, traveling towards NY.
Oh man, Matt you must have seen a ghost train. Since JIm says another 4-6 months til we see a test train
This was a double decked car. I thought thats what they were using. Are the double decked ones to the football and baseball special trains?
hey, I’m not a train spotter. :)
Matt, you probably saw the NJ transit double-decker that takes fans to Giants Stadium on game-day on Sunday. See: http://www.westportnow.com/index.php?/v2/comments/takng_the_train_to_the_game/
The new Metro North railcars, if we ever get them, are one-deck because the tracks between New Rochelle and Grand Central can’t accomodate double-deckers I believe.
Next entry: Blackening the Ovals
Previous entry: Polls Open to Light Turnout
life issues.
Groups Psychotherapy
www.drannabram.com
Top
Driver,
the nation's premier driving school, is now in Westport at
830 Post Road East